PassedPittsburgh will pay Toole Design, LLC up to $204,274 for Phase 2 of the West Pittsburgh REACH Neighborhood Mobility Plan. This plan aims to improve neighborhood mobility. The payment is an increase of $100,000 from the previously executed agreement.
Official title›
Resolution providing for a supplemental Agreement or Agreements with Toole Design, LLC for costs associated with Phase 2 of the West Pittsburgh REACH Neighborhood Mobility Plan, and providing for the payment of costs thereof, not to exceed Two Hundred Four Thousand Two Hundred Seventy-Four Dollars ($204,274.00), an increase of One Hundred Thousand Dollars ($100,000.00) from the previously executed agreement.
- Topic
- Streets & transit
- Money
- $204,274city spends
- Who it affects
- West Pittsburgh residents
- Sponsors
- —
Recipient: Toole Design, LLC. supplemental agreement. Where: West Pittsburgh.
neighborhoodsmobilitydesigninfrastructureplanning
Record
What happened, and who voted how
Passed · Passed Finally8–0, 1 absent
- Anthony CoghillY
- Barbara WarwickY
- Bobby WilsonY
- Erika StrassburgerY
- Khari MosleyY
- Kim SalinetroY
- R. Daniel LavelleY
- Robert CharlandY
- Deborah L. Gross—
Source text
From the legislative file
..title Resolution providing for a supplemental Agreement or Agreements with Toole Design, LLC for costs associated with Phase 2 of the West Pittsburgh REACH Neighborhood Mobility Plan, and providing for the payment of costs thereof, not to exceed Two Hundred Four Thousand Two Hundred Seventy-Four Dollars ($204,274.00), an increase of One Hundred Thousand Dollars ($100,000.00) from the previously executed agreement. ..body Be it resolved by the Council of the City of Pittsburgh as follows: Section 1. The Mayor and the Director of the Department of Mobility and Infrastructure, on behalf of the City of Pittsburgh, are hereby authorized to enter into a supplemental Agreement or Agreements with Toole Design, LLC for costs associated with Phase 2 of the West Pittsburgh REACH Neighborhood Mobility Plan, and providing for the payment of costs thereof, not to exceed Two Hundred Four Thousand Two Hundred Seventy-Four Dollars ($204,274.00), an increase of One Hundred Thousand Dollars ($100,000.00) from the previously executed agreement, to be paid from the following account(s): JDE Job No. JDE Fund Budget Year Previous Amount Current Amount Total Amount Source 6029400477 29040 N/A $99,500.00 $100,000.00 $199,500.00 Grant 6074012523 40123 2023 $4,774.00 - $4,774.00 PayGo $104,274.00 $100,000.00 $204,274.00 TOTAL
Streets & transit
Related items
- 2026-0459Pittsburgh will pave Elwell Street from Mere Street to the city limits with asphalt. The project is on a street currently made of concrete. No cost was specified.
- 2026-0475Pittsburgh will pay $125,000 to repave Hazelwood Trail between Blair Street and the Hot Metal Bridge. The work is part of a cooperation agreement with Friends of the Riverfront. The trail is located in the Hazelwood neighborhood.
- 2026-0534Pittsburgh will reimburse up to $1,000,000 for the Beaver Avenue Esplanade Project. The Pennsylvania Department of Transportation will cover the costs. The project is for the Study and Preliminary Design phases.
- 2026-0586Pittsburgh will pay Cyclomedia Technology, Inc. up to $814,936.75 over 9 years for access to 360 GeoCycloramas and LiDAR data for city-owned roads. This will help with streetlight and telecommunication attachment inventory. The city is increasing its approved spending by $46,590.
- 2026-0591Pittsburgh will reimburse Verizon for up to $6,500 for work on the City Steps project. Verizon will pay the city back for the costs. The project is located in the area of City Steps - Potomac.